Following projects of GSECL are
under
implementation:
1.
2X250 MW
Coal based Extension
Unit
3 & 4 at Sikka.
Order placed on M/s. BHEL on EPC basis.
| Zero date of the
project |
22.05.2007 |
|
Schedule of commissioning of
Unit
3 |
June 2012 |
|
Schedule of
commissioning of
Unit
4 |
August 2012 |
|
EPC
Cost in Rs. Lacs |
228200.00 |
2.
500 MW Coal Based Extn Unit 6 at Ukai.
Order placed on M/s. BHEL on
EPC basis.
| Zero date of the
project |
06.10.2007 |
|
Scheduled commissioning of
Unit
6 |
July
2011 |
|
Boiler Drum placed in
position on |
31.12.2009 |
|
EPC
Cost in Rs. Lacs |
221800.00
|
3.
Projects
under Active consideration:
1.
395 MW Gas Based CCPP
Stage-III at Dhuvaran.
Consent to establish (NOC)
from
GPCB and for chimney construction
(for height) from
Airport
Authority are
available.
2.
1X800 MW Coal Based Extn. Unit
No.8 at WTPS. |