 (A) Following Units were put in commercial Operation by GSECL in 2009-10:

  1. Gas Based 375 MW CCPP Stage-II at Utran Power Station

  2. Lignite Based 75 MW Unit no. IV at Kachchh Lignite TPS, Panandhro.  

 (B) Following projects of GSECL are under implementation:

1. 2X250 MW Coal based Extension Unit 3 & 4 at Sikka.

     Order placed on M/s. BHEL on EPC basis.

 Zero date of the project  22.05.2007
 Schedule of commissioning of Unit 3  June 2012
 Schedule of commissioning of Unit 4  August 2012
 EPC Cost in Rs. Lacs  228200.00

2. 500 MW Coal Based Extn Unit 6 at Ukai.

    Order placed on M/s. BHEL on EPC basis.

 Zero date of the project  06.10.2007
 Scheduled commissioning of Unit 6  July 2011
 Boiler Drum placed in position on  31.12.2009
 EPC Cost in Rs. Lacs  221800.00 

   3.  Projects under Active consideration:

      1.   395 MW Gas Based CCPP Stage-III at Dhuvaran.

       Consent to establish (NOC) from GPCB and for chimney construction

       (for height) from Airport Authority are available.

           2.  1X800 MW Coal Based Extn. Unit No.8 at WTPS.

 (C) Following Projects are under various stages of Planning:  

1  4X800  MW  Coal Based Units at Kuchhadi, Dist. Porbandar
2  2X800  MW  Coal Based Units at Sinor, Ta. Sinor, Dist. Vadodara
3  2X800  MW  Coal Based Units at Dahej, Dist. Bharuch 
4  2X1000 MW  Gas Based Power Plants in North Gujarat

 

 